Reverie at Marcato

This project consists of target repairs to miscellaneous penetrations throughout the building. Improperly integrated WRB and mis-lapped flashing are in most part the culprit in causing the need for repair. Our crew is working steadily at making great progress on this project, keeping on track with the tight schedule in needing to have this project completed before the harsh winter weather arrives. As of November 1st, we have completed the South, West and North elevations excluding some minor items which will be completed shortly. Our crew will be working on the final elevation this month. FullSizeRender